ADEC Logo

Skip Navigational Menu and go to Main Page Content
What's New
About ADEC
Privacy Policy
Security and Privacy
Shop at the ADEC E-Store
IDEAL
Learning Resources
Courseware Tools
Satellite Resources
Federal Programs and Grants
Agricultural Telecommunications
NSF Project
eArmyU
Internet and Electronic Trends
Accessability Issues
Standards and Plans
International Cooperation
Conferences and Workshops
Virtual Universities
Internal Management
Search
Help
Distance Education... Distance Education... Distance Education...

Capital and Operating Costs for a Full-Time National Video Channel:

Report by ADEC Digital Infrastructure Task Force
All ADEC Meeting:
Tuesday, March 7, 2000


ADEC plans to implement a twenty-four hour a day, seven day a week (24/7) video channel that can be broadcast by EchoStar, DirecTV and cable operators and be received in the home, workplace and in ADEC member learning centers.

Cost estimates are provided for three operational categories:

  • Head-End Carriage
  • Technical Support and Engineering at the Channel Aggregation Location
  • Program Management

HEAD-END CARRIAGE:

Capital Costs:
None.

Operating Costs:
EchoStar and DirecTV are charging a monthly fee to most programmers (FCC 98-307). Fees are subject to change pending the outcome of FCC evaluation of ADEC Informal Complaint regarding EchoStar charges. ADEC expects that cable headends will carry the ADEC Channel on public access space without charge.

Monthly Fee-DirecTV-currently @ $6,350/mo for most applicants: $76,2000
Monthly EchoStar @ $10,372/MO: Alt.$124,464
Total:


$76,200 Alt.$124,464

TECHNICAL SUPPORT AND ENGINEERING AT THE CHANNEL AGGREGATION LOCATION:

The ADEC Channel Aggregation Location will:

  • Receive programming from ADEC members. The Internet will be the recommended first choice for program delivery. Programming may also be delivered on videotape or DVD. Live programming will be received on a scheduled basis by Internet or by analog or digital satellite.

  • Programming will be aggregated into a seamless 24/7 ADEC Channel Program Schedule.

  • Aggregated programming will be encoded into MPEG II for transmission to the DBS and cable headends over broadband Internet. Channel mapping data will also be maintained and transmitted to the headends from this location.

  • The Channel will be monitored and customer support will be provided.

The Channel Aggregation Location cost estimates are represented in two stages.

Stage I:
This period will cover the startup phase of operation for the ADEC Channel. Stage I will have an estimated duration of one to two years. Costs are based on the assumption that the vast majority of programming will be provided to the Channel Aggregation Center via broadband Internet or on video tape or DVD. Live programming may be delivered on a tightly managed schedule via Internet or schedule for reception on the host site's existing satellite downlink facilities. This stage would also provide for the delivery of programming from members during off-peak (late night) periods via IP multicasting and broadband Internet for delayed retransmission on the ADEC Channel. The aggregated ADEC Channel programming schedule will be transmitted to DBS and cable headends over the broadband Internet backbone.

Only the quality control and testing necessary to meeting minimum requirements of the DBS or cable providers will be installed during this stage.

Stage II:
This stage may simply be a continuation and improvement of the facilities and services provided in Stage I. It is anticipated, however, that increased demand for live programming will require the addition of dedicated satellite backhaul facilities and the addition of improved monitoring and testing equipment and procedures. ADEC will continue to encourage members to transmit most live and delayed programming to the Channel Aggregation Center on the broadband Internet. It is possible that more sophisticated digital editing and production equipment may be required as well as some additions to studio facilities. ADEC anticipates that increasing numbers of cable providers, some of which can only receive programming from satellite feeds, will be candidates for carriage of the ADEC Channel.

Capital Costs:

The business plan assumes that some existing equipment located at the NCC host site will be used during Stage I and that charges for use of this equipment will be budgeted under operating expenses. The business plan assumes that this condition will continue into Stage II, and that additions to the equipment inventory will be added incrementally out of annual capital budgets to either supplement or replace host site equipment.

CAPITAL COST SUMMARY
Stage I
Stage II

Digital IRDs; Magnitude, Wegener: $ 3,000  
Digital IRDs; PowerVU, NDS:   $ 3,000
Backhaul Receive Antenna w/4-port feed, 2Ku & 2 C LNBs Steerable with de-icing:   $15,000
Analog Receiver, Antenna control Unit and additional DigiCipher II IRD:   $ 4,000
Digital Encoding for Ku-Band Satellite Uplink, Single Channel MCPC:   $125,000
Amplifiers, monitors and test equipment: $10,000 $25,000
S-VHS Tape Deck $ 4,600  
Beta-SP Tape Deck-Play only: $13,640 $13,640
Beta-SP Tape Deck-Record/Play:   $20,500
Digital Editing Suite: $25,000 $40,000
Total:


$56,240


$246,140

Operating Costs:

Estimates for Personnel costs at the NCC include benefits:

Sr. Management @ 0.5 FTE. The expense represents an assessment to support the Sr. management services provided by the Host Site: $47,200
Engineering @ 1.5 FTE. This expense will support engineering contributions by the Host Site for the 24/7 operation of the ADEC Channel: $79,080
Technical & Support @ 4.5 FTE. Represents Para-professional responsibilities for operating the 24/7 ADEC Channel: $118,000
Clerical @ 0.5 FTE: $15,150
Total Personnel:

$259,430

Estimates for Non-Personnel Direct Operation Costs:

Transit Charges for delivery of Aggregated ADEC Channel to DBS and Cable headends:

Transit over broadband Internet backbone from the Host Site @ $5,000/month:

Alternate: Transit of 4.5 MHZ digital channel on Galaxy K& @ $27,500:

$60,000



Alt. $330,000

Terrestrial Telecommunication Charges @ 400/month: $ 4,800
Utilities and Expendable Supplies: $15,200
Amortization for Host Site Equipment: $20,000
Total Direct:

$100,000 Alt. $370,000

PROGRAM MANAGEMENT:

Capital Costs:

Computer Hard/software -- 2 @ $25,000: $ 5,000
Total:

$ 5,000

Operating Costs:

Estimates for Program Management Personnel Costs Including Benefits:

Program Manager @ 1.0 FTE. This is a Senior Management Position in charge of management, oversight and marketing for the ADEC Channel: $90,000
Administrative Assistant @ 1.0 FTE. This is a mid-level management position: $40,000
Total:

$130,000

Non-personnel direct operating cots are incorporated into the annual ADEC operating budget.

SUMMARY:

Capitol Costs (one-time expenditure) Stage I Stage II

Head-End Carriage: $0 $0
Tech/Engineering: $56,240 $246,140
Program Management: $5,000 $0
Total:

$61,240

$246,140

Operating Costs (annual):
The differences between the Standard and Alternate estimates provide a low and high estimate of operation costs for the system based on the assumption outlined above.

  Stage I Stage II

Head-End Carriage: $76,200 $124,464
Tech/Engineering: $359,430 $629,430
Program Management: $130,000 $130,000
Total:

$565,630

$883,894
 